Independent review of the Inland Rail project reveals huge cost blowout and poor governance

Conor Burke
Updated April 7 2023 - 6:38pm, first published 5:00am
The current route for the now $31 billion Inland Rail project travels along the existing rail corridor which cuts through the middle of Wagga. Picture by Les Smith
The current route for the now $31 billion Inland Rail project travels along the existing rail corridor which cuts through the middle of Wagga. Picture by Les Smith

The massive cost blowout and lack of direction of the Inland Rail revealed by the independent review of the project should '"set alarm bells ringing" and be cause for a major rethink of the route.

Subscribe now for unlimited access.

or signup to continue reading

All articles from our website & app
The digital version of Today's Paper
Breaking news alerts direct to your inbox
Interactive Crosswords, Sudoku and Trivia
All articles from the other in your area
Conor Burke

Conor Burke

Journalist

Conor covers Wagga city council, business and defence, but is definitely interested in your quirky story. Mobile: 0400 311 335 EMAIL: conor.burke@dailyadvertiser.com.au

Your morning news Newsletter

DAILY

Your morning news

Today's top stories curated by our news team.